10 UNIT SIX: CREDITORS’ RIGHTS AND BANKRUPTCY
29-8A. SPECIAL CASE ANALYSIS—Liens
Case No. 29.1
Picerne Construction Corp. v. Castellino Villas
California Court of Appeal, Third District, 2016
244 Cal.App.4th 1201, 199 Cal.Rptr.3d 257
(a) Issue: What statutory term was the focus of the dispute in this case? Why? The
statutory term at the center of the dispute in the Picerne case can be found in California Civil
Code Section 3115, which covered mechanic’s liens when Picerne, the plaintiff and contractor in
this case, filed its lien against Castellino, the defendant and property owner. That statute
provided, “Each original contractor, in order to enforce a lien, must record his claim of lien after
he completes his contract and before the expiration of 90 days after the completion of the work
of improvement.”
In a related statute, the term completion was defined as “actual completion of the work.”
This provision also deemed the acceptance by the owner or his agent of the work to be
equivalent to completion.
Picerne had contracted to build an apartment complex for Castellino Villas in a city in
California. During the project, the city had issued certificates of occupancy for the different
buildings on various dates, with the last certificate issuing on July 25. Later, Picerne employees
and subcontractors had done substantial work. Castellino had not rented any of the apartments
until October.
With the contract price unpaid past its date, Picerne had filed a mechanic’s lien on
November 28. Later, Picerne had filed a suit in a California state court to foreclose on the lien. In
the suit, the parties had disputed the meaning of the term “completion” as it appeared in the
state lien statute and applied to the circumstances of their case. Their different interpretations of
the meaning of the term affected a determination of whether Picerne’s filing of its liens had been
timely. (b) Rule of Law: Under the state statute that applied in this case, what must a party
show to enforce a lien? To enforce a lien under the state statute that applied in this case, a party
must show that it is an original contractor, that it had a contract for a work of improvement
owned by the party against whom enforcement of the lien is sought, that the lien has been
recorded, and that its filing occurred with ninety days after the completion of the work.
Picerne contracted to build an apartment complex for Castellino Villas in a California city.
The city issued certificates of occupancy for different buildings within the complex on various
dates, releasing the last certificate on July 25. Beyond that date, Picerne employees and
subcontractors did substantial work on the project, and Castellino did not rent any of the
apartments until October. On November 28, with the contract unpaid, Picerne filed a mechanic’s
lien and later a suit to foreclose on the lien.
At contention in the suit was the meaning of the term completion. None of the other
elements of the lienor’s case was disputed.